i have a project that is baselined in MS Project. I upload to Daptiv but when I run the report showing planned and actual finish for the milestones. the actual and planned finish dates are the same (mapping to the actual) - it doesn't seem to keep the baselined "planned" finish date.)
Baseline reports may only be reported against Daptiv baselines, not MSP baselines. You can not Daptiv baseline a sync'd schedule, and you must do independent baselines in daptiv for imported files.